January Lakeview Apartments Update

We are proud to provide the latest update for our flagship Rockingham development. Currently we have the following blocks under construction

Block 3 - final electrical, plumbing and painting

Block 8 - painting, kitchen installs, roof, external plastering

Block 4 - first floor brickwork

Block 7 - footings excavated