Rockingham & Hamilton Hill Updates - 1st March 2018

ROCKINGHAM

Block 3 - Final paint, fire stair installed, building powered

Block 4 - Electrical tubing underway, form-work, concrete steel work

Block 5 & 6 - Earthworks complete

Block 7 - Retaining walls in progress

Block 8 - Carpentry, waterproof tiling, cabinets installed, ceilings & white set to walls



HAMILTON HILL

Unit 1-2 Suspended slab curing. Bricklaying to commence shortly

Unit 3-5 Kitchens and ground floor ceilings to be installed shortly

Unit 6-9 Lock up floors screeded, waterproofing and kitchen installs

Unit 10-17 Fit off plumbing and electrical. Shower screen and mirrors installed

Unit 18-21 Tiling underway